Billings publishes large-diameter pipe projects, from 54-inch reinforced concrete pipe on Wicks Lane to raw-water piping up to 48 inches for the West End Water Treatment Plant.
This page covers the right-of-way permits Billings uses, what they cost, how far ahead to file, and what pipe-scale work means for how your lifting crews are qualified.

Training Services Offered in Billings
Based in Albuquerque, our instructors travel to you. Train at your own facility, or we'll arrange a rented site nearby. Either way, your crew trains on the crane they actually run.

On-Site Training
On‑site training is designed for companies that have the facilities and equipment available at their own location and prefer to keep their employees onsite for logistical or operational reasons. All on‑site training requires the company to provide the crane or equipment that will be used during the training and evaluations.

Off-Site Training
Off‑site training is intended for customers who do not have the facilities or space to conduct training at their own location. Paradise Crane Consultants will arrange a suitable rented facility; however, the company must still provide the crane or equipment needed for the training and evaluations.
Local permitting and municipal requirements
Billings Public Works, Engineering Division administers right-of-way work. The two permits to know are the Traffic Control Permit and the Encroachment Permit under City Code § 13-301. Both cover public right-of-way, not crane operation itself. Submit the Traffic Control Permit at least one week before work and wait for approval. Local streets classified LOCAL with ADT under 500 are excepted, but Engineering must still be notified of the work description and duration.
The Traffic Control Permit application is listed as free. The Encroachment Permit application is $75 on the City's current page, while the linked form states $65 effective September 26, 2022. Confirm current fees with the city.
Traffic control must meet MUTCD and ADA requirements, and the permit must show staging areas, haul routes and pedestrian access routes. Owners and Contractors Protective coverage of $1,000,000 each occurrence and $2,000,000 aggregate applies to City public-works construction contracts, not as a confirmed limit for private right-of-way permits. Confirm insurance, closure hours and crane-placement hours with Engineering before you mobilize.
Local industry and employment
Yellowstone County carries 87,416 covered jobs (BLS QCEW, 2025 annual average), with average annual pay of $64,980. Construction accounts for 5,926 of them, or 6.8%, at $78,225 average annual pay. Manufacturing adds 3,851 jobs, or 4.4%, at $92,975.
The dated work in Billings is municipal infrastructure. A City report dated May 10, 2024 described Phase II of the Wicks Lane stormwater replacement: about 1,400 feet of piping, including 54-inch reinforced concrete pipe and a water-quality treatment device. A City bid notice dated May 2, 2025 covered Grand Avenue water main replacement, with two sections of 20-inch main plus fittings, valves, hydrants and service reconnections. A bid notice dated May 29, 2025 covered 24-, 30-, 36-, 42- and 48-inch fiberglass-reinforced polymer mortar pipe between the raw-water pump station and the West End Water Treatment Plant.
Crews working pipe at these diameters should qualify every role on the lift, not just the operator.
Does Montana require a state crane operator license on top of federal OSHA rules?
Montana is not an OSHA-approved State Plan, so federal OSHA covers most private-sector workers in the state. State and local government workers are not covered by federal OSHA in Montana; Montana DLI describes a separate state public-sector workplace safety inspection program.
The governing construction crane standard is 29 CFR Part 1926, Subpart CC, including 29 CFR 1926.1400 et seq. Section 1926.1400 sets the scope as power-operated equipment used in construction that can hoist, lower, and horizontally move a suspended load. That citation is specific to construction. General-industry crane and hoist use is governed by separate standards, including 29 CFR 1910.179.
What sets Montana apart is licensing. Montana DLI states that a person operating crane or hoist equipment used to hoist or lower personnel or material, with a manufacturer's rating of more than 6 tons, must first obtain a Department of Labor license. The Crane / Hoisting Operator Program administers it.
29 CFR Part 1926 Subpart CC; 29 CFR 1926.1400; 29 CFR 1926.1427; 29 CFR 1910.179
Is NCCER certification enough on its own?
Montana's license is class-based. The third-class crane oiler pathway lists age 18 or older and a written examination, with no experience or physical examination. The second- and first-class operator pathways describe experience, a written examination, a practical examination where applicable, and a current physical examination.
Montana's official application instructions list NCCER certification or card among the documentation for the national-certification reciprocity pathway. That describes state licensing reciprocity. It does not establish that any listed credential alone satisfies every federal OSHA requirement, so confirm current acceptance with the DLI Crane / Hoisting Operator Program.
The federal baseline still applies. Under 29 CFR 1926.1427, operators must be certified by an accredited testing organization or an audited employer program. Certification is valid for five years, and the employer pays for it. Before an operator runs covered equipment unsupervised, the employer must evaluate the operator on the assigned equipment and document it. Montana's license is an additional requirement and does not replace these.
What does the workplace safety data show?
The U.S. Bureau of Labor Statistics Census of Fatal Occupational Injuries (CFOI) puts Montana's fatal work injury rate at 5.8 per 100,000 full-time-equivalent workers in 2024, down from 7.1 in 2023.
These figures cover all industries, not cranes specifically.
What should you verify before your next lift?
Before your next covered lift in Montana, work through these checks:
- Confirm jurisdiction. Federal OSHA covers most private-sector workers, while state and local government workers fall under Montana DLI's separate public-sector program.
- Confirm the work is construction use under 29 CFR 1926 Subpart CC. General-industry crane use is governed by separate standards, including 29 CFR 1910.179.
- Confirm whether the equipment needs a Montana license: crane or hoist equipment rated at more than 6 tons. Overhead trolley and gantry cranes are included only when used in construction, and equipment with excavation attachments or log-loading equipment is excluded when in use.
- Verify each operator's license through the DLI Crane / Hoisting Operator Program and its Professional and Occupational Licenses public portal.
- Confirm each operator's federal certification is current for the equipment type.
- Keep the documented employer evaluation for that specific equipment available at the worksite.
Upcoming certification and training sessions dates
Questions
Which Billings permit applies when lift work affects the street?
The Traffic Control Permit covers City right-of-way work. Submit it at least one week before construction begins and get approval before work starts. Full road closures need owner approval. Full closures of arterials or collectors also need a signed detour using other arterials and collectors, plus changeable message signs at the closure point for both travel directions. Sign lead time runs from 1 business day for a 1-2 day closure up to 5 business days for 9 or more days. A lane or full closure on an arterial, or a full closure on a collector, also needs an approved news release furnished at least three days before work starts. The City code text for the Encroachment Permit does not specify whether it applies to temporary crane placement, so confirm with Engineering.
What do Billings right-of-way permits cost?
The Traffic Control Permit application is listed as free. The Encroachment Permit application is $75 on the City's current page, while the linked application states $65 effective September 26, 2022. Resolution 22-11063, adopted September 12, 2022, sets annual encroachment rental at $2.00 per square foot or linear foot for Tier 1 and $3.80 for Tier 2, each with a $20 minimum annual fee per encroachment. Tier 2 covers major impacts that make the right-of-way unusable to the public. Confirm current fees with the city.